2016 is here! See our progress...

Guymon:

Here is the current status of our homes on blazing trail!

16 homes have been framed

15 have been decked

11 homes have roofs

13 have had plumbing top outs

8 have received the HVAC roughs.

Coming up, we will be scheduling meetings to go over your new home prior to sheetrock beginning. This will be the time to make any last minute door swing or electrical adjustments and to verify plan is as it should.

Our time frame is currently April on receiving the Certificates of Occupancy. This date is an estimate and could change should there be any setbacks out of our control.

Please contact Andy Falls for any questions: 580-651-4663

PONCA:


Come visit our Ponca location and see our newly constructed, ready to move in homes!

Contact Angela for an appt. 580-977-7781