Our houses are moving along, check out the progress

GUYMON

28 plumb roughs are complete, remaining should be complete next week.

21 slabs are poured, four more will be poured next week.

Six houses are framed, three more will be framed next week.

Four houses are sheathed and corniced, three more will be sheathed next week.

Three houses are decked, three more will be decked next week.

The plumber will begin topouts next week.

The roofer will begin roofing the week after next.

All of the utilities should be run by the end of next week. We should be able to start working on the roads week after next. Check back for more updates soon in Guymon. For any questions, please call Andy at 580-651-4663

ENID

In Enid we had inspections to the first 11. The plumb, mechanical, and building inspections have passed. Second 11 in Enid are through trim and we will begin installing tile on Monday following electric trims that following weekend.

More info. soon! Please call Angela with any questions. 580-977-7781