See whats new this week!

ENID


We still should receive a certificate of occupancy on the first eleven before Thanksgiving.

We are hoping to schedule the final walks on 12/7.

The second 11 will be trimmed and painted within the next couple of weeks. We will possibly have certificate of occupancy before the New Year and final walks starting the beginning of the year.

For questions or more information: Angela Elliott 580-977-7781

GUYMON


There are 26 houses that are currently plumb roughed, the remaining will be roughed in this weekend.

There are currently 15 slabs poured, 5 more will be poured next week.

Currently 2 houses framed and 5 more will be framed next week.

The utilities should be complete within two weeks, at that time they will begin working on the road.

For questions and more information: Julie Lollman 580-277-1144

PONCA

Final inspections completed early next week, we will be getting the houses ready for final walks next week.

For more information or questions: Angela Elliott 580-977-7781